August 14, 2017 8:50 AM

Lake/Cross Street Improvement Project: Work Scheduled for 8/14-8/18:

Lake/Cross Street Improvement Project: Work Scheduled for this week:

Work scheduled for week of 8/14/17 -8/18/17
~Fine grade and roll Cross street reclaimed area (except unfinished sewer area)
~Complete Sanitary Sewer and Manhole Installation
~Prep School driveway and Bissell Road entrance for paving
~Reset Manhole cover at Bissell Road
~Pave Binder
~Install Bit Curbs
~Complete drainage work at intersection of Cross Street and Lake Street
~Install Speed Indicators conduit and bases
~Continue to water grass on edges as necessary
~Alternating one way traffic will be encountered during grading and paving and at drainage work areas